We got the excavation/foundation portion of our permit from the city on Friday so today was the day: the big dig. It started early but got off to a slow start. The excavation company only had two trucks which then hauled the dirt across town to Stillwater. Our contractor was finally able to summon up more trucks in the afternoon. That helped tremendously. At the end of the first day most of the area was dug out but it was only 3'-4' deep. Tomorrow the digging should be finished. Hopefully, the rain will stay away so we can start the footings.
Jason and I have never so excited to see a hole dug in our entire life. Now if we can get the rest of our permit approved....(need more info on the beams).
Will post photos when I find the camera...